Dorrance - Sat. 11/24 @ 9am
A few more loose ends to tie up and U.R. Phase II will be ready to open. Just basic trail building at this point; tech features will be added over winter and spring 2019.
Planning another build day Saturday 11/24 @ 9:00 am. We're past the crazy benching work and back into moderate slopes. This might be the last dirt moving/working day of the season due to incoming freeze.
Meeting in the inner parking lot (directions here) by the Playground. Gates are locked for the season but will be unlocked & closed while we're working if you need to get in/out (keep them closed). See map below for work area if you arrive late and need to find us. We'll be working for ~3 hrs.
Work Plan:
- Bench <70yds of trail
- Scrape/rake in <70 yds of trail
- Shape/compact a couple dozen rollers/berms along length of Phase II
- Rock armor a stream crossing
- Pickup flagging materials
Tools Needed: (Extra tools will be available)
- Rogue Hoes
- Flat Shovels
- A couple wheelbarrows
- Vibrating Plate Compactor and/or Hand Tampers
Work Area Map:
Photos from Last Workday:
If you've never volunteered for a trail work session check this out: Things to Know Before Volunteering for Trail Work
⚒ Trails don't build themselves. ⚒