This weeks Dorrance trailwork plan:
Thursday 6/30 @ 5:30pm - Building Switchbacks
Saturday 7/2 @ 9:00am - Building Switchbacks
Rogue hoes and flat shovels are needed. As always, I'll have extra tools available.
Meeting near the bathrooms in the inner parking lot at the times listed above and working for a couple of hours. Get directions to the park here. See the map below for how to get to the work area if you can't make it that early.
Click to Enlarge
Please RSVP if you plan on coming.
Keep an eye on this topic for weather related changes.
Never built trail before? Click here for a quick rundown of what to expect and how to prepare.
Update: We battled the heat last week but still managed to punch out 250 yds of trail! This puts us at 0.9 miles of trail completed so far.
Check out more photos of progress here: Dorrance Trailbuilding Gallery